The story of the new Parkcrest Elementary School begins with a tragic fire that destroyed the former school on September 5, 2019. At that time, the District, staff, and community came together to support students and families and ensure the Parkcrest Elementary community stayed together. On September 16, 2019, Parkcrest students were relocated to George Hilliard, where they remained until the end of the 2023-2024 school year. 

George Hilliard had previously been the home of the Alternative Education Program for secondary students, (Twin Rivers Education Centre) and (program of Choice for Aboriginal high school students). (Alternative Education Program for middle school students) was located at the former John Tod facility leased by the City of Kamloops for the Boys and Girls Club. These three programs (TREC, Four Directions, Bridges) are currently at Happyvale.

On January 25, 2021, a new, expanded, and energy efficient Parkcrest Elementary School design was announced. With an investment of $34.84 million from the Government of BC and $300,000 from the Kamloops-Thompson School District, the new Parkcrest was designed with a larger capacity of 510 seats to help prepare for expected enrollment growth in the community. The City of Kamloops also committed up to $2.5 million for the additional space required for a larger gymnasium and change room facilities for sporting events.

Construction on the new school began in 2022 and the newly rebuilt Parkcrest Elementary School welcomed student back at the start of 2024-2025 school year in September 2024. Students, staff, and the community marked this momentous occasion with a celebratory event on Wednesday, September 4, 2024. Read more about the Parkcrest Elementary School Opening here

Milestones
Rebuild of Parkcrest Elementary School (K-7) - Join the Journey and See the Build in Action
2019
Dec. 18, 2019 - Kamloops Fire Chief issues statement following conclusion of Parkcrest Elementary fire investigation.
Sept. 27, 2019 - ÌÇÐÄSwag News Parkcrest Elementary sings at Kamloops Blazers game and hockey-goers donate more than $8,000 for Parkcrest Elementary School.
Sept. 23, 2019 -  Thank you to the community for generous donations.
Sept. 23, 2019 -  Elementary Students Relocate to George Hillard and TREC Students Relocate to Happyvale.
Sept. 16, 2019 - Parkcrest families start first day at George Hilliard.
Sept. 16, 2019 - ÌÇÐÄSwag News Parkcrest students began their school year again at George Hilliard Elementary.
Sept. 10, 2019 - Minister of Education shares message about Parkcrest rebuild.
Sept. 9, 2019 - ÌÇÐÄSwag News Parkcrest Recovery Plan presented to Board, staff, and parents/guardians of students — Parkcrest students and staff moving into George Hilliard Elementary.
Sept. 6, 2019 - Community reacts to loss of Parkcrest Elementary.
Sept. 5, 2019 - News reports ‘Kamloops elementary school destroyed in massive fire’.
Sept. 5, 2019 - ÌÇÐÄSwag News Tragic fire closes Parkcrest Elementary until further notice.
Sept. 5, 2019 - Fire Tragic Fire
2020
Sept. 4, 2020 - Superintendent Sullivan shares Parkcrest update one-year after fire.
June 22, 2020 -  Parkcrest identified as first priority in 2021-2022 Capital Plan.
Feb. 13, 2020 - ÌÇÐÄSwag News Parkcrest students share thank you message for Kamloops.
Jan. 16, 2020 - ÌÇÐÄSwag News Parkcrest Fire Investigation Completed.
Jan. 14, 2020 - News reports on Parkcrest Elementary Fire Incident Report.
Jan. 15, 2020 -  Parkcrest Elementary Fire Incident Report reviewed by the Board of Education.                             
2021
Nov. 22, 2021 - Neighbourhood Learning Centre community engagement consultation plan presented to the Board.
June 24, 2021 - Students and teachers get a glimpse of Parkcrest replacement school.
Jun. 22, 2021 - 
Design for New Parkcrest School Revealed—students and staff experience a virtual walk through the new school.
April 21, 2021 Capital Engagement Committee established - reviewes and provides input on elements of the design of the school.
Mar. 3, 2021 - ÌÇÐÄSwag News
Architect Announced - Station One Architects (formerly CHP Architects) of Chilliwack, BC selected.
Feb. 16, 2021 - Parkcrest Elementary School Rebuild update presented to the Board.
Feb. 3, 2021 - Education Minister Jennifer Whiteside shares a message about Parkcrest Elementary School’s new beginning.
Jan. 26, 2021 - News reports on Parkcrest rebuild update.
Jan. 25, 2021 Request For Proposals for an architect made public.
Jan. 25, 2021 - ÌÇÐÄSwag News New, larger school for Parkcrest students, community announced.

Jan. 25, 2021 - 

Ministry approval for the Parkcrest Elementary rebuild.
2022
 
April 11, 2022 - Parkcrest Elementary Replacement Project update provided to the Board.
April 2022 - Construction Update Construction on the the new Parkcrest Elementary School officially begins. 
Mar. 31, 2022 - News reports Parkcrest Elementary School construction to begin in spring 2022.

Mar. 31, 2022 - ÌÇÐÄSwag News

Contractor Announced — Dawson Wallace Construction selected to rebuild Parkcrest Elementary.
2023
Nov. 1, 2023 See the Build-in-Action
Front entrance - siding underway

Front entrance - siding underway

Parking lot - paving completed, landscaping underway

Parking lot - paving completed, landscaping underway

Typical classroom - west wing

Typical classroom - west wing - painting underway, flooring underway

Typical classroom - west wing

Typical classroom - west wing - painting underway, flooring underway

West wing hallway - painting underway

West wing hallway - painting underway

Playground installation almost complete

Playground installation almost complete - just waiting for the wood fiber installation

Playfield - sod is complete

Playfield - sod is complete

June 6, 2023

See the Build-in-Action

 North end of east hallway looking north

North end of east hallway looking north.

Status: Interior steel studs well underway

 Main entrance Main entrance.

Status: Mechanical and electrical rough-in underway

 NLC space looking east NLC space looking east.

Status: Interior steel studs well underway

 Typical classroom

Typical classroom. 

Status: Interior steel studs well underway

 Looking at field from gym roof Looking at field from gym roof. 

Status: Site - stripping of existing grass complete

 Gym Gym. 

Status: Roofing - complete except for the gym

April 3, 2023 See the Build-in-Action

West classroom block. 

Status: Structural steel complete

NLC area. 

Status: Mechanical and electrical underground rough in - complete

Gym. 

Status: Exterior framing and sheathing - 50% complete

North side of west wing. 

Status: Slabs - 20% complete

West side of north wing. 

Status: Roofing - 70% complete

 2024
 
Sept. 4, 2024 -  Parkcrest students share their excitement for returning to Parkcrest Elementary School and what they like about their new school. 
Sept. 4, 2024 -  News reports on Parkcrest Opening: Five years after tragic fire, Parkcrest Elementary welcomes students back to a brand-new school.
Sept. 4, 2024 - ÌÇÐÄSwag News Release Kamloops-Thompson School District and Board of Education celebrates the opening of the new Parkcrest Elementary School.
Sept. 4, 2024 -  New Parkcrest Elementary School opens in Kamloops.
Sept. 3, 2024 - First day of school Students return to Parkcrest Elementary on the first day of the 2024-2025 school year. 
June 11, 2024 Child care RFP opens: New RFP for child care (T24031), specific to the newly built Parkcrest Elementary, becomes available on BC Bid. The RFP encompasses two rooms: Infant/Toddler and 3-5-year-old. The RFP is open from June 11 to August 9, 2024 (4pm).
May 6, 2024 - 

Deputy Minister Christina Zacharuk, Assistant Deputy Minister Jennifer McCrea, and Associate Superintendent of Indigenous Education Brad Baker visit the Kamloops-Thompson School District and tour the new Parkcrest Elementary School.

Deputy Minster Visit Deputy Minster Visit Deputy Minster Visit Deputy Minster Visit

Feb. 14, 2024 -  News reports students to return to Parkcrest Elementary in September 2024.
Feb. 12, 2024 -  The Board supports the first day for students to attend the rebuilt Parkcrest Elementary School to be Tuesday, September 3, 2024.
Jan. 31, 2024 See the Build-in-Action
Image 01

Special Education room looking towards outside wall

Image 02

Gymnasium looking towards north wall

Image 03

Gymnasium looking at ceiling towards southeast corner of gym

Image 04

Looking down west corridor from office area

Image 05

Typical classroom looking towards outside wall

Image 06

Typical classroom looking toward hallway wall

Image 07

Library looking south to outside wall

Image 08

Front entry area looking at library

How to get Involved

Watch for updates here and through social media.

Questions can be sent to: Facility Input

If you would like to post as we provide updates, please go to:

  • Facebook:
  • Instagram:
  • X:

Contact Us